A construction company
contracted ProAct Services Corporation to
provide water treatment services for the Paper Plant Construction
Project. The company had planned to directly discharge construction pond
water directly to a near by river. When the water was tested, it was
found to contain mercury and other contaminants above the allowable
discharge limits. The client needed to find a company to treat the pond
water in a hurry to keep from shutting down the construction activities
at the site.
ProAct was contacted on October 17 about the project. We
mobilized equipment and personnel to treat water at 5,500 gallons per
minute for hydrocarbons and heavy metals in
six days!
ProAct was treating water on October 23. We
provided media vessels, bag filter systems, flow meters and hoses, and
manufactured a custom manifold for the treatment system.
ProAct Services has four water treatment
specialists working two 12 hour shifts each day, 7 days a week to
operate the water treatment system.
ProAct operated continuously for 66
days until the construction was complete on December 21.
During the project,
ProAct had to take measures to freeze
protect the water treatment system including wrapping exposed hoses with
heat trace, insulting exposed valves and gauges, and insulating the
exposed hoses on the ground.
Frequent water recirculation was used during nights where the
temperature dropped below 32 degrees F.
Safety
ProAct Services employees have worked a total of 2345 hours from
October 23 to December 21 without a reportable accident.
|