| 3,000 GPM Pipeline Discharge Water Treatment | |
|
ProAct used mobile carbon and sand filters to filter water at a flow rate of 3,000 gallons per minute to keep up with the water removal rate from a pipeline hydrotest in California. Water was pushed out of the pipeline into a series of frac tanks and then treated by ProAct. |
|
| A problem with the suspended solids in
the sand filter back wash water was encountered early in the project. The solids were not settling before the next back wash event. ProAct responded within 24 hours to install a coagulating polymer injection system to speed the removal of solids from the back wash water. This modification restored the ability to treat water at 3,000 GPM. The project had zero accidents and was successful! |
|
| Volume: 327,441 barrels/13.8M gallons | |
| Flow Rate: 71 BPM/3,000 GPM | |
| Discharge Monitored for: Iron,
Oil & Grease, Total suspended solids, Total Dissolved Solids and pH |
|
![]() |
![]() |
![]() |
![]() |
| Call
Peter Horrall
at (210)862-6467 or email
horrall@proact-usa.com
for a custom quote. Peter has years of field experience working with challenging sites and is uniquely qualified in getting you exactly what you need for your site. We do it right and we do it right NOW! |
|